CONSTRUCTION UPDATES - PHOTOS
Progress of the Future EHS Animal Center

 

Photos

       Click on any image to see a larger version

October 21, 2002
A panoramic view of the site, prior to grading.

 

October 25, 2002
Grading is underway.


November 22, 2002
Building pad grading complete, ready to dig footings.

 

December 16, 2002
Footings complete, ready to put up walls.


December 30, 2002
Walls going up; preparing for the foundation pour.


January 7, 2003
Drying out after the big rains.

 

January 16, 2003
Concrete foundation being poured.


January 29, 2003
Walls being finalized, windows and doors being set. Steel supports for overhangs and roof trusses being set up.
Also, a view down the hallway between the stray cat area and the stray dog holding area.


February 18, 2003
The heavy rains didn't dampen our spirits: More great progress has been made!
Sewer lines installed, walls erected and about ready for the new steel roof, and the Petco Courtyard is coming along nicely.


March 18, 2003
The facility is coming along nicely. From left to right are:
Animal receiving area, back entrance, courtyard view of building, hallway framing, Petco courtyard, and inside framing going up.


April 7, 2003
More progress has been made. The views are of the front and right side of the new building.